LTA, SMRT and SBST to progressively refurbish over 500 escalators across NSEWL, NEL and CCL

Joint News Release Issued by LTA, SBS Transit and SMRT

19 November 2026 - The Land Transport Authority, and the rail operators, SMRT and SBS Transit, will progressively refurbish 290 escalators across the North-South and East-West Lines (NSEWL) and North East Line (NEL) to enhance safety, reliability and commuter comfort.  This will be progressively carried out from 17 Dec 2026, and all refurbishment works are expected to be completed by 2032. Another 237 escalators on the Circle Line (CCL) will also be refurbished, with works scheduled to commence at a later date1. 

The refurbished escalators will feature enhanced safety and operational features such as an in-built voice announcement system for safety announcements, LED indicators to indicate the direction of travel, and improved illumination. Similar to earlier refurbished escalators, the escalators will be able to operate at dual speeds – at regular speed during peak hours to facilitate smooth commuter flow, and at a slower speed during off-peak hours for energy conservation purposes and to better serve the aging population.

This refurbishment programme builds on SMRT’s earlier upgrading of 231 escalators across the NSEWL, which was completed in 2022. This latest phase will cover 83 escalators along the NSEWL that were not due for upgrading under the earlier programme. 

Refurbishment Works and Commuter Access 

The refurbishment of each escalator is expected to take approximately four to five months. The works involve the replacement and upgrading of key mechanical and electrical components, including the motor, control equipment, steps, handrails and safety features. 

Where a station has multiple escalators scheduled for refurbishment, works will be carefully sequenced to minimise inconvenience to commuters and the overall duration of works. Within stations, at least one up-riding escalator will remain in service to carry passengers from the platforms to the concourses, and to the entrances.  Lifts will also remain available for commuters who require them throughout the refurbishment period. Directional signs will be implemented to guide commuters to available lifts, stairs and other alternative routes. Commuters who require assistance may approach station staff.

The refurbishment programme also includes escalators adjacent to stations, such as at Pedestrian Overhead Bridges (POBs). At these POBs, there is only one escalator on each side of the bridge. While the refurbishment works are being carried out, there will be no upward-moving escalator available on the affected side of the bridge. Commuters can use lifts, stairs or other alternative routes via pedestrian crossings to access the station during this period.

Continued Renewal of Escalators Across the Rail Network

LTA will continue to work closely with rail operators to progressively renew and upgrade ageing escalators across the rail network. These ongoing efforts will help to ensure that our escalators continue to operate safely and reliably for commuters.

1More details on the commencement of works for the CCL escalators will be announced in due course.

Annex: Escalator Refurbishment Process